How do I price my first federal quote?
Build your price from the bottom up. Add your direct costs, then your overhead, then your profit. Then check the number against the wage rules in the solicitation and against what the government has paid before.
You found a request for quote (RFQ) that fits your business. You can do the work. Then you reach the price sheet and freeze. Price too high and you lose. Price too low and you win a contract that loses money every month.
Step 1: Read exactly what you are pricing
Before any math, find these in the RFQ:
- The line items (often called contract line items, or CLINs) and the quantity for each
- The period of performance, including any option years
- Where and when the work or delivery happens
- The price format the agency wants, such as a fixed price per month or a price per unit. The contract type tells you who pays if costs run over
- How price will be judged, which is usually in the evaluation section
That last one matters. Some buys go to the lowest-priced quote that meets the requirements. Others weigh price against quality. The solicitation tells you which.
Step 2: Add up your direct costs
Direct costs are what you spend only because of this contract:
- Labor: hours times pay rate for each person
- Materials and supplies
- Travel, if the work requires it
- Subcontractors, if you use them
Check for a wage determination. Many service and construction contracts include one. It sets the minimum pay and benefits you must give workers in that area. The Service Contract Act covers many service contracts over $2,500. The Davis-Bacon Act covers federal construction contracts over $2,000. You can look up wage determinations on SAM.gov without logging in. If one applies, your labor cost can’t go below it. On construction jobs, also budget the weekly certified payroll. See Davis-Bacon and certified payroll.
Step 3: Add your overhead
Overhead is what it costs to run your business: rent, insurance, software, accounting, and your own time spent on admin. Spread a fair share of it across each contract. Many small firms do this as a percentage of direct costs. Work out your real number from last year’s books. Don’t borrow someone else’s.
Step 4: Add profit
Profit pays for the next proposal, slow payments, and surprises. Pick a margin that keeps your business healthy if the work takes longer than planned.
Step 5: Check your price against the market
Now compare your number with what the government already pays:
- GSA CALC+ Ceiling Rates. This free tool from the General Services Administration (GSA) shows the maximum hourly labor rates on GSA schedule contracts. You can filter by labor category, experience, education, and business size. No login is needed. Remember these are ceiling rates. Real prices on orders are often lower.
- Past awards. Award amounts for federal contracts are public. Search past awards for the same agency and type of work to see a realistic range. Contract award search moved into SAM.gov in February 2026 and now needs a free SAM.gov account.
If you are far above that range, look for costs you can cut. If you are far below it, check for something you missed.
A worked example
This example uses made-up numbers. It is not a real wage determination or a recommended profit rate.
A small cleaning company is pricing one year of office cleaning: two workers, 20 hours a week each, for 52 weeks.
| Cost | How it’s figured | Amount |
|---|---|---|
| Labor hours | 2 workers × 20 hrs × 52 weeks | 2,080 hours |
| Wages and required benefits | 2,080 hrs × ($18.00 wage + $5.42 health and welfare) | $48,713.60 |
| Payroll taxes and workers’ comp | 12% of wages ($37,440) | $4,492.80 |
| Supplies | Estimate for the year | $3,000.00 |
| Direct cost total | $56,206.40 | |
| Overhead | 10% of direct costs | $5,620.64 |
| Profit | 8% of cost plus overhead | $4,946.16 |
| Yearly price | $66,773.20 (about $5,564 per month) |
The company would then check that the $18.00 and $5.42 figures match the actual wage determination in the RFQ. The $5.42 rate assumes a contract with required paid sick leave, so it would add that leave’s cost, which this example leaves out. It would also compare the monthly price with past awards for similar buildings.
Mistakes that hurt new contractors
- Skipping the wage determination. You may have to pay more than you planned, with no way to raise your price later.
- Pricing to win at any cost. A price that loses money can sink a small business. It can also look unrealistic to the buyer.
- Forgetting option years. If the contract can run several years, think about raises and rising supply costs. Check whether the solicitation lets you price each year differently.
- Ignoring the price format. A price in the wrong format can get your quote set aside.
- Leaving out your own time. The hours you spend managing the contract are a real cost.
Rules worth knowing
- Micro-purchase threshold: $15,000. Below this, agencies can often buy with fewer steps.
- Simplified acquisition threshold: $350,000. Most buys at or below this use simpler procedures, and many are set aside for small businesses.
- Both amounts took effect on October 1, 2025.
- The Federal Acquisition Regulation (FAR) overhaul has proposed moving simplified buying rules into a different part of the FAR. That change was still a proposal as of October 15, 2026, so the thresholds above are the ones in effect.
A quote is not an offer. Read our guide A quote is not an offer to see what that means for your RFQ response.
Do this in FedPath
Check your labor rate against GSA ceilings. Before you set an hourly rate, see the ceiling rates companies hold on GSA schedules for the same role. They are ceilings, not prices paid. Free, with no account.
Research GSA labor ratesSearch open opportunities
Free. FedPath is independent. It is not affiliated with, endorsed by, or part of the U.S. government, the Small Business Administration (SBA), SAM.gov, or any federal agency.
Common questions
What is the micro-purchase threshold in 2026?
It is $15,000. It rose from $10,000 on October 1, 2025.
Can I see what other companies charged?
Partly. Award amounts are public, and GSA’s CALC+ tool shows ceiling labor rates on GSA schedule contracts. Detailed pricing inside a competitor’s quote is not public.
Do I have to pay the wage determination rate?
If the contract includes a Service Contract Act or Davis-Bacon wage determination, you must pay at least those wages and benefits to covered workers.
Does the lowest price always win?
No. Some buys go to the lowest price that meets the requirements. Others trade price against quality. The evaluation section of the solicitation tells you which. See [lowest price or best value](/government-contracting/lpta-vs-best-value/).