Dates to know
- SBA’s bond guarantee fee rises to $7.29 per $1,000
If a surety company won’t bond you on its own, the Small Business Administration (SBA) can back the bond so the surety will. That help has a fee, and for many contractors it goes up on November 30, 2026. The jump is $1.29 for every $1,000 of contract. On a small job that’s a few hundred dollars. It still belongs in your price, and on jobs you bid now it may apply after you’ve set that price.
What SBA’s bond guarantee does
Many federal construction jobs need a performance bond and a payment bond. A surety company issues those bonds, and it decides how much risk it will take on you. Newer and smaller firms often get turned down.
SBA’s Surety Bond Guarantee program helps with that. SBA tells the surety it will cover part of the loss if you don’t finish the job. With that promise, the surety is more willing to bond you. SBA can back bonds on federal contracts up to $14 million, and up to $9 million on other work. For the basics of each bond, see what bid, performance and payment bonds are.
Bid bond guarantees have no SBA fee. The fees below apply to the bonds you need after you win, which are the performance and payment bonds.
What changed
On October 30, 2026, SBA published a notice in the Federal Register. It raises two fees in the Prior Approval program, the part of SBA’s program where SBA approves each guarantee before the surety issues the bond:
| Who pays | Before | From November 30, 2026 |
|---|---|---|
| You, the contractor | $6.00 per $1,000 of contract amount | $7.29 per $1,000 of contract amount |
| Your surety | 20% of the bond premium | 26% of the bond premium |
The new fees apply to guarantees SBA approves on or after November 30, 2026. What counts is the date SBA approves the guarantee. The date you bid or win doesn’t matter.
The new rates are a return to old ones. SBA lowered both fees in 2018 to see what a cut would do. It says the Prior Approval program has run short of money since then.
Who doesn’t pay more
Two groups keep the old rates of $6.00 per $1,000 and 20% of the premium:
- Manufacturing projects: jobs under North American Industry Classification System (NAICS) codes that start with 31, 32 or 33.
- The Preferred program: bonds from sureties that SBA lets issue guaranteed bonds without asking it first.
If you don’t know which program your surety uses, ask your bonding agent. It decides which fee you pay.
What it costs on a real job
Hypothetical: a paving company wins a $500,000 federal job. Its surety is in the Prior Approval program, and SBA approves the guarantee on December 3.
| Before | From November 30 | |
|---|---|---|
| SBA fee | $3,000 | $3,645 |
| Difference | $645 more |
SBA rounds each fee to the nearest dollar. The contractor’s fee is paid when the surety sends SBA the paperwork for the final bond. If the contract amount goes up later, the fee can go up too.
The surety’s share also rises, from 20% to 26% of the premium you pay it. SBA’s notice doesn’t say whether sureties will pass that on to you. SBA’s rules limit a surety to the premium your state’s insurance department allows, so ask your agent whether your premium will change.
What to do now
- Ask your bonding agent two questions. Is my surety in the Prior Approval or the Preferred program? When will SBA likely approve the guarantee on my next job?
- Price the higher fee into bids now. A bid you send in November may not reach SBA approval until December. Use $7.29 per $1,000 unless you’re sure the old rate applies.
- Check your industry code. If the job is in manufacturing (31–33), the fee stays at $6.00 per $1,000.
- Don’t wait to start. Bonding takes time. If you’ll need a bond soon, call your agent this month.
If a bid is due before you know the answer, use the higher number. Overpricing a $500,000 job by $645 is a small risk. Underpricing it means paying the difference yourself. What it costs to respond to a government RFP covers the other costs to count.
Common questions
How much is the SBA surety bond guarantee fee?
For guarantees the Small Business Administration approves on or after November 30, 2026, a contractor whose surety is in the Prior Approval program pays $7.29 per $1,000 of the contract amount, up from $6.00. Manufacturing projects and the Preferred program stay at $6.00, and bid bond guarantees are still free.
Does the date I bid decide which fee I pay?
No. The new fee applies to guarantees the Small Business Administration approves on or after November 30, 2026. A bid you send in November can still get the higher fee if the guarantee is approved in December.