What is a request for equitable adjustment on a federal contract?
It’s a written request to the contracting officer for more money or time because the government changed the work, and it usually starts a negotiation. If you can’t agree, you can file a claim, which asks for a formal decision. Claims must be filed within 6 years.
You did what the government asked. Maybe a site wasn’t ready, the agency wanted a different part, or the work grew. Now your costs are higher than your price. You can ask to be paid for that, but how you ask, and when, matters.
Getting paid for a change
Give written notice
You
As soon as you know. Under the fixed-price Changes clause, within 30 days of a written order.
Send a request for equitable adjustment
You
What changed, who asked, and the added cost and time, with proof.
Negotiate
The agency
Most end here, with a signed modification.
File a claim
You
An exact amount and a request for a final decision, within 6 years. Certify claims over $100,000.
Final decision
The agency
Within 60 days, or a date for it on claims over $100,000.
Appeal
You
To the agency board within 90 days, or the Court of Federal Claims within 12 months.
Sources: FAR 33.206 · 41 U.S.C. 7103 · 41 U.S.C. 7104 · FAR 52.243-1. Checked Oct 23, 2026. The solicitation decides the details.
First, give notice
Getting paid for a change starts with telling the contracting officer, in writing, as soon as you know about it. Many contracts set a deadline. Under the standard fixed-price Changes clause, you have 30 days after a written change order to ask for an adjustment. See contract changes and who can approve them.
This guide picks up after notice: how to ask for the money.
Step 1: the request for equitable adjustment
An REA is a business request, not a legal fight. It says what changed, why it’s the government’s change, and what it cost you. A good one includes:
- What the contract required, with the section or clause.
- What changed, who asked and when, with emails and meeting notes attached.
- The cost, broken down: labor hours and rates, materials, subcontractor costs, overhead and profit, and any delay.
- Extra days, if you need more time to finish.
- Proof: timesheets, invoices and receipts tied to the change.
Most REAs end with a signed modification that adds money, time or both. That’s the goal.
Step 2: a claim, if you can’t agree
If negotiation stalls, you can file a claim under the Contract Disputes Act. The Federal Acquisition Regulation (FAR) defines a claim as a written demand seeking, as a matter of right, “the payment of money in a sum certain.” What makes it a claim:
- It’s in writing and goes to the contracting officer.
- It asks for an exact amount.
- It asks the contracting officer for a final decision. You can say so directly: “This is a claim under the Contract Disputes Act. Please issue a final decision.”
A normal invoice that isn’t in dispute isn’t a claim. Courts have also found that an REA can count as a claim if it asks for a final decision, so the words you use matter.
| Rule | What it says |
|---|---|
| 6-year limit | Submit the claim within 6 years after it accrues. Your contract may set a shorter limit. |
| Certification | Claims over $100,000 need a signed statement that the claim is in good faith, the data is accurate and complete, the amount is what you believe you’re owed, and the signer is authorized. |
| Decision time, $100,000 or less | The contracting officer must decide within 60 days if you ask for a decision in that time. |
| Decision time, over $100,000 | Within 60 days, the contracting officer must decide or tell you when they will. |
| No decision | If the deadline passes with no decision, you can treat it as a denial and appeal. |
If the decision goes against you
You can appeal a contracting officer’s final decision in one of two places:
- The agency’s board of contract appeals, within 90 days of receiving the decision.
- The U.S. Court of Federal Claims, within 12 months of receiving the decision.
These deadlines are strict. Miss them and the decision usually becomes final, so talk to a government contracts attorney well before the deadline.
Keep working, and get help early
Under the standard clauses, you generally have to keep working while you disagree. Stopping work can put you in default. See cure and show-cause notices.
Get help if the amount is large, if the contracting officer says no, or if you’re close to a deadline. An APEX Accelerator can help you organize an REA. For a claim or an appeal, talk to a government contracts attorney. See free help with government contracting.
Key terms
- Request for equitable adjustment (REA)
- A written request for a fair change in price, schedule or both, because the work changed. It usually starts a negotiation.
- Claim
- A written demand for an exact amount of money you’re owed under the contract, which asks the contracting officer for a final decision.
- Sum certain
- An exact dollar amount. “About $40,000” or “at least $40,000” isn’t one.
- Final decision
- The contracting officer’s formal written answer to a claim. It starts the clock for an appeal.
- Contract Disputes Act (CDA)
- The law that sets the rules for claims on most federal contracts.
Do this in FedPath
Show what the contract required. Your compliance matrix is a record of what the original solicitation required. Use it to show what’s new when you write an REA.
Open the compliance matrixContract changes
Free. FedPath is independent. It is not affiliated with, endorsed by, or part of the U.S. government, the Small Business Administration (SBA), SAM.gov, or any federal agency.
Common questions
Do I need a lawyer to file an REA?
No. An REA is a business request, and many small businesses write their own. For a claim, especially one over $100,000, a lawyer’s review is a good idea.
Will asking for more money hurt my CPARS rating?
A fair, well-documented request shouldn’t. Your rating is about performance. Stay professional and keep working. See [CPARS](/government-contracting/cpars/).
Can I include the cost of preparing the REA?
Sometimes. The rules on these costs depend on why they were spent and when, so ask your contracting officer or an advisor before you add them.
Is a claim the same as a bid protest?
No. A protest challenges how a contract was awarded. A claim is about money or terms on a contract you already have. See [bid protests](/government-contracting/bid-protests/).