Can a government program manager ask me to do extra work on my contract?

They can ask, but only the contracting officer can change your contract. If you do extra work without a signed modification, you may not be paid for it. Tell the contracting officer in writing and wait for the signed modification before you start.

A few weeks into a contract, the person you work with every day asks for “one more thing.” It sounds small, and you want to keep the customer happy. But the person asking may have no power to change your contract. If you say yes, you could end up doing the work for free.

Before you do extra work

Only the contracting officer can change your contract.

  1. Someone asks for more

    The agency

    Often the COR or the program manager. Note who asked and when.

  2. Check the contract

    You

    If the work is already in the statement of work, it isn’t a change. Do it.

  3. Tell the contracting officer

    You

    In writing, the same day: what was asked, by whom, and what it would cost.

  4. Wait for a signed modification

    The agency

    Usually on an SF 30. Don’t start the work or buy for it before then.

  5. Do the work and log it

    You

    Keep timesheets and receipts tied to the change.

Sources: FAR overhaul · FAR 43.104 · FAR 43.103. Checked Oct 22, 2026. The solicitation decides the details.

Who can change your contract

Only a contracting officer, acting within their authority, can sign a change to your contract. Other people you deal with can’t, even if they run the program or approve your invoices. That includes:

  • The contracting officer’s representative (COR), who checks your work.
  • The program manager or end user.
  • A contract specialist who isn’t a warranted contracting officer.

These people can tell you what they need. They can’t promise to pay for it. Your contract and award letter name your contracting officer, so keep that name at the top of your contract file.

Two kinds of modifications

Bilateral and unilateral modifications
BilateralUnilateral
Who signsYou and the contracting officerOnly the contracting officer
Common usesAgreed price changes, added work you negotiated, other new termsChange orders, exercising an option, administrative changes like a new address, termination notices
Your sayYou can negotiate before you signYou don’t sign, but you may be owed an adjustment

Either kind is usually written on a Standard Form 30 (SF 30).

Which clause is in your contract

Commercial contracts (FAR 52.212-4)

Most small businesses sell commercial products or services, and those contracts use clause 52.212-4. It says changes “may be made only by written agreement of the parties.” In plain words, both sides have to agree in writing.

Other fixed-price contracts (FAR 52.243-1)

Many other fixed-price contracts use the Changes clause, 52.243-1. It lets the contracting officer order some changes alone, by written order. For a supply contract, that covers drawings, designs or specifications, how items are shipped or packed, and where they’re delivered. If the change raises your cost or time, you’re owed an equitable adjustment.

  • Ask for the adjustment within 30 days of getting the written order.
  • Keep working on the contract as changed, even while you disagree about the price.

To check, search your contract’s clause list for 52.212-4 or 52.243.

When someone asks for extra work

  1. Check the contract. If the work is already in the statement of work, it isn’t a change. Do it.
  2. If it’s new, say so politely: “I’m happy to help. This looks outside our current scope, so I need to check with the contracting officer before we start.”
  3. Write to the contracting officer. Say what was asked, who asked, when, and what it would cost in time and money. Copy the person who asked.
  4. Wait for a signed modification before you do the work or buy anything for it.
  5. Log it: the date, who asked, what, your notice and the answer.

Changes nobody wrote down

Sometimes the government changes your work without calling it a change. A COR might insist on a higher standard than the contract asks for, or a work site might not be ready on the date the contract says. People sometimes call these constructive changes.

Tell the government in writing as soon as possible. Some contracts include clause 52.243-7, Notification of Changes, which spells out this duty. After your notice, the government can confirm the change, tell you to stop, or tell you it isn’t a change. Late notice makes it much harder to get paid.

If you already did the work

Work done because someone without authority asked is an unauthorized commitment, and it doesn’t bind the government. The agency can sometimes approve it afterward through ratification, but only if several conditions are met, such as the government getting the benefit, a fair price and money being available. It’s slow and not guaranteed, so don’t plan on it.

Pricing a change, and when to get help

When you ask for an adjustment, show your math: the added hours, materials and any delay, using the rates in your contract where they apply. Keep timesheets and receipts tied to the change.

If the change is large, if the contracting officer says it’s in scope and you disagree, or if you’ve already spent money, talk to your local APEX Accelerator or a government contracts attorney. See free help with government contracting.

Key terms

Modification
A written change to a signed contract, usually on Standard Form 30 (SF 30).
Bilateral modification
A change both you and the contracting officer sign. Also called a supplemental agreement.
Unilateral modification
A change only the contracting officer signs, such as a change order or exercising an option.
Equitable adjustment
A fair change to the price, the schedule or both, because the work changed.
Unauthorized commitment
An agreement made by a government employee who had no authority to make it. It doesn’t bind the government.

Do this in FedPath

Keep a record of what’s in scope. The free compliance matrix tool lists every requirement in the solicitation. Keep it after award as your record of the scope, and check new requests against it.

Open the compliance matrixYour first 30 days

Free. FedPath is independent. It is not affiliated with, endorsed by, or part of the U.S. government, the Small Business Administration (SBA), SAM.gov, or any federal agency.

Common questions

The COR approved it by email. Is that enough?

Usually not. A COR normally can’t change the contract. Ask the contracting officer for a signed modification.

Can the government change my contract without my signature?

In some cases, yes. A change order or an option exercise is unilateral. You may be owed a price adjustment if the change adds cost.

Do I have to keep working if we disagree?

Under the standard clauses, yes. You keep working while the disagreement is settled.

Is exercising an option a change?

It’s a unilateral modification, but it isn’t new work. It follows option terms already in the contract.