What should I do if I get a cure notice on a federal contract?
Note the deadline, usually 10 days after you received it, and fix the problem if you can. Before the deadline, answer in writing with what went wrong, what you’ve done and your plan with dates. Ignoring it can lead to termination for default.
A letter from the contracting officer says you’re not meeting the contract, and it gives you a deadline. It’s a serious warning, and it’s also a chance to fix things. Contractors who answer on time, with facts and a plan, give themselves the best chance of keeping the contract.
How a contract problem can lead to termination
A concern is raised
The agency
Often informal. Fix it and confirm in writing.
Cure notice
The agency
Usually 10 days to fix the problem. A good fix can end it here.
Show-cause notice
The agency
Usually 10 days to explain why you shouldn’t be terminated.
Your response
You
Each problem, what you’ve done, your plan with dates, and any real excuse with proof.
The decision
The agency
The contracting officer weighs your reasons before any termination for default.
Sources: FAR 49.402-3 · FAR 49.607 · FAR 12.403. Checked Oct 22, 2026. If you miss a firm delivery date, a cure notice may not come first.
The two notices
| Cure notice | Show-cause notice | |
|---|---|---|
| What it says | You’re failing to meet the contract. Fix it. | Explain why we shouldn’t terminate you for default. |
| Deadline | 10 days after you receive it, or longer if the contracting officer allows | 10 days after you receive it, in the FAR’s sample notice |
| What you do | Fix the problem and report back | Explain, with facts, why termination isn’t justified |
| If you don’t respond | The contracting officer can move to termination for default | Silence may be treated as an admission that you have no good explanation |
A cure notice usually comes when you’re failing part of the contract or falling so far behind that the work is at risk. A show-cause notice often comes after a deadline has passed or a cure notice didn’t fix things.
Late delivery is different
On a commercial contract, the contracting officer must send a cure notice before terminating for any reason other than late delivery. So if you miss a firm delivery date, a cure notice may not come first. If you know you’ll be late, tell the contracting officer in writing before the date.
Your first 10 days
- Day 1: find the deadline. Write down the date you received the notice and the response date. If the deadline is unclear, ask in writing.
- Day 1: confirm you got it, in a short email to the contracting officer that says when you’ll respond.
- Days 1 to 3: find the real cause. Talk to your team and subcontractors, and pull schedules, emails, delivery logs and inspection reports.
- Days 2 to 7: fix what you can. Fixing the problem is the strongest answer you can give.
- Before the deadline: send your written response by a method that leaves a record, and keep a copy.
What to put in your response
A response the contracting officer can use
0 of 5 checked
On commercial contracts, a delay is excusable if it’s caused by something beyond your reasonable control, such as acts of God, acts of the government, fires, floods, strikes or carrier delays. You must tell the contracting officer in writing as soon as it happens.
Don’t blame the government without evidence, and don’t promise dates you can’t meet. Missing a second promise is worse than the first problem.
What the contracting officer weighs
Before terminating for default, the contracting officer must consider the contract terms and the law, your reasons for the failure and whether they hold up, whether someone else could do the work and how fast, how urgent the need is, and any other facts that matter. Give them facts they can use and a believable path to finishing the work.
Why it matters, and when to get help
A termination for default is serious. You may not be paid for work the government didn’t accept, you may owe the government damages, and it can hurt future bids. If a termination for default later turns out to be wrong, it’s treated as a termination for convenience. See termination for convenience.
Get help when the notice arrives, not on day 9. A government contracts attorney can review your response, especially to a show-cause notice. Your local APEX Accelerator can help you organize records and a plan. See free help with government contracting.
Key terms
- Cure notice
- A written warning that you’re failing to meet the contract, with a deadline, usually 10 days, to fix it.
- Show-cause notice
- A written notice asking you to explain why the contract shouldn’t be terminated for default.
- Termination for default
- The government ends your contract because you didn’t perform. Commercial contracts call it termination for cause.
- Excusable delay
- A delay caused by something beyond your reasonable control, such as a flood, a strike or an act of the government.
Do this in FedPath
Check your capacity before you bid. The Bid/No-Bid tool asks whether you have the people and capacity to do the work. Answer it honestly before you commit.
Free. FedPath is independent. It is not affiliated with, endorsed by, or part of the U.S. government, the Small Business Administration (SBA), SAM.gov, or any federal agency.
Common questions
Is a cure notice the same as being fired?
No. It’s a formal warning with a chance to fix the problem.
Can I get more time?
Ask in writing before the deadline and explain why. The contracting officer can allow longer.
Will a cure notice affect my CPARS rating?
The problems behind it can affect your performance rating, and a good recovery can be noted too. See [CPARS](/government-contracting/cpars/).
What if the government caused the problem?
Say so with documents, such as late government approvals or missing site access. If the government changed the work, see [contract changes](/government-contracting/contract-changes/).