On a services contract set aside for small businesses, no more than half of what the government pays you can go to subcontractors that aren’t similarly situated. People call it the 50 percent rule. It exists because the government wants a small business to do the work.
Two words first. The prime contractor is the business whose name is on the contract. A subcontractor is a business the prime hires to do part of the work. On a set-aside, the prime must be small. The rule is about how much the prime can pay its subcontractors.
The rule comes from clause 52.219-14 of the Federal Acquisition Regulation (FAR). It also comes from the Small Business Administration (SBA) rule at 13 CFR 125.6. On a services contract, you may not pay more than 50 percent of what the government pays you to subcontractors that are not “similarly situated.” Supplies work the same way, with the cost of materials left out. If you resell products you don’t make, the nonmanufacturer rule also applies. Construction is looser: 85 percent for general construction and 75 percent for specialty trades such as plumbing or roofing, again leaving out materials.
“Similarly situated” is the tricky part. It means a subcontractor that has the same small business status the contract was set aside for, and is small under the industry code for the work it does. On a plain small business set-aside, that is any small business. On a service-disabled veteran-owned (SDVOSB) set-aside, it is a certified SDVOSB. Money you pay to a similarly situated partner does not count against your 50 percent, as long as that partner does the work with its own employees instead of passing it along to someone else.
The rule is measured on what the government pays over the whole contract, not on each invoice. It applies to every kind of set-aside. That includes 8(a), HUBZone, women-owned (WOSB) and service-disabled veteran-owned (SDVOSB) contracts. The contracting officer can ask you to show your numbers. Breaking the rule means breaking your contract.
- Decide who will be the prime. If a large partner would do most of the work, it may need to be the prime, with you as its subcontractor. Prime contractor vs subcontractor explains the tradeoffs.
- Add up the dollars, not the tasks. The rule counts money paid, so price each company’s share before you sign a teaming agreement or form a joint venture, and write the split down.
- Check your partner’s status. A partner only counts as similarly situated if it holds the same set-aside status and is small for its part of the work. Ask, and keep the answer.
- Read the solicitation. It names the clause, and some agencies add their own notes on how they count. If anything is unclear, ask the contracting officer before you bid.
This rule is one of the capability checks in what to do after finding a contract on SAM.gov. If you need a partner to deliver the work, make sure the partnership keeps you on the right side of the 50 percent line.