I won a spot on an IDIQ contract. Why haven’t I gotten any work?
Most multiple-award contracts only promise a small minimum, and the real work comes as task orders. Above the micro-purchase threshold, every holder usually gets a fair chance to be considered for each order. You still have to find, bid and win each one.
Winning a spot on a big multiple-award contract feels like crossing the finish line. A $5 billion ceiling sounds like a lot of money, but it’s a limit shared by every company on the contract. Your share depends on the orders you win next.
What you can expect on a task order
At or below the micro-purchase threshold
- The agency can pick any holder
Check: No competition required
Above the micro-purchase threshold
- Every holder gets a fair chance to be considered
- Unless an exception applies
Check: Watch for order requests sent to holders
Over $7.5 million
- A notice to all holders
- The main evaluation factors
- A written basis for the award
- A debriefing if you lose
Check: Ask for the debriefing
Over $10 million ($35 million at DoD, NASA and the Coast Guard)
- A protest is possible, at GAO only
Check: Protest deadlines are short
Orders that go beyond the contract’s scope, period or maximum value can be protested at any size.
Sources: FAR 16.505 · FAR overhaul · FY2025 NDAA increases the threshold for DoD task order protests. Checked Oct 22, 2026. The solicitation decides the details.
What you actually won
A multiple-award IDIQ is a contract held by several companies. It sets prices or rates, terms and a ceiling, and it promises each holder only a minimum, which is often small. The agency then buys through task orders for services and delivery orders for supplies.
A General Services Administration (GSA) Schedule works in a similar way. See should your small business get a GSA Schedule?
Fair opportunity: the basic rule
When an agency places an order above the micro-purchase threshold under a multiple-award contract, it must give every holder a fair opportunity to be considered, unless an exception applies. Your rights get stronger as the order gets bigger.
| Order size | What you can expect |
|---|---|
| At or below the micro-purchase threshold | The agency can pick any holder. |
| Above the micro-purchase threshold | Every holder gets a fair chance to be considered. Smaller orders can be run more simply, for example a short request sent to holders by email. |
| Over $7.5 million | A notice to all holders, a clear description of the work, a reasonable time to respond, the main evaluation factors and their importance, a written basis for the award, and a debriefing if you lose. |
For the current micro-purchase and simplified acquisition thresholds, see micro-purchases and contracts under $350,000.
When an agency can skip fair opportunity
An agency can give an order to one holder without competing it in a few cases:
- The need is so urgent that competing it would cause unacceptable delays.
- Only one holder can do the work, because it’s unique or highly specialized.
- It’s a logical follow-on to an order that was already competed among all holders.
- The agency needs to meet a holder’s minimum guarantee.
- A law says to buy from a specific source.
- The order is set aside for small businesses.
After a sale or merger with a company that isn’t small, you may have to recertify as other than small. On a set-aside multiple-award contract, that ends your chance at set-aside orders.
For sole-source orders above the simplified acquisition threshold, the agency must post its justification on SAM.gov within 14 days, for at least 30 days. Reading these shows you who gets work without competition.
Protests are limited
You generally can’t protest a task order. There are two exceptions:
- The order goes beyond the contract’s scope, period or maximum value.
- The order is over $10 million at most agencies, or over $35 million at the Department of Defense (DoD), NASA and the Coast Guard. These protests can only go to the Government Accountability Office (GAO).
So for most orders, your best tools are a good debriefing and a better next bid. See debriefings and bid protests.
How to win orders
- Know who orders. Many IDIQs can be used by more than one office. Find the ones that buy what you do.
- Introduce yourself after award. Send each ordering office a short note with what you do and your contract number.
- Watch for order requests. Some come through the contract’s own portal or by email, not SAM.gov. Make sure the right people at your company get them.
- Bid selectively. Use the same go or no-go thinking you’d use for any bid.
- Track your minimum. If the government hasn’t ordered it near the end of the contract, raise it with the contracting officer.
Key terms
- IDIQ
- Indefinite delivery, indefinite quantity. A contract that sets terms and prices but not exact amounts. The agency orders as needs come up.
- Task order and delivery order
- An order under an IDIQ. Task orders are for services, delivery orders for supplies.
- Fair opportunity
- The rule that each holder of a multiple-award contract gets a fair chance to be considered for each order above a small dollar amount.
- Minimum guarantee
- The smallest amount the government promised to order from you under the contract.
Do this in FedPath
Follow the notices for your vehicles. Browse opportunities and save the notices for vehicles you hold or want. FedPath tells you when a saved notice changes, such as a new amendment or due date.
Explore opportunitiesContract vehicles
Free. FedPath is independent. It is not affiliated with, endorsed by, or part of the U.S. government, the Small Business Administration (SBA), SAM.gov, or any federal agency.
Common questions
Is my minimum guarantee a promise of work?
Yes, but only up to the minimum amount stated in the contract, and that amount is often small.
Do I see every order request on SAM.gov?
Not always. Orders don’t have to be posted the way new contracts are. Some go only to holders through the contract’s own channels. [Where order requests are posted](/government-contracting/find-task-orders/) lists the channels.
Can I lose my spot for not winning orders?
It depends on the contract. Some have rules for removing holders who don’t bid or perform, so read yours.