What indirect cost rate can I use on a federal grant if I don’t have a negotiated rate?
Under the federal grant rules, you can charge up to 15% of your modified total direct costs if you don’t have a negotiated rate, and you don’t have to document it. The National Institutes of Health (NIH) is an exception for now: it uses a 10% flat rate for most applicants, and lets small businesses applying for Small Business Innovation Research (SBIR) or Small Business Technology Transfer (STTR) awards propose up to 40% of total direct costs.
Your grant budget has a line many first-time applicants skip: indirect costs. Leave it out and you pay your own rent, phone and bookkeeping while you run the project. Get the rate or the base wrong and your budget won’t add up. Here is how the flat rate works, which costs it applies to, and where NIH does it differently.
Direct costs vs. indirect costs
Direct costs are tied to the project. Say you pay someone for 800 hours to run a workshop series. Their pay is a direct cost. So are the workbooks and the trips to each site.
Indirect costs keep your organization running. Rent, utilities, insurance, accounting and computer support serve every project at once. You can’t send one bill to one grant, so you charge a percentage instead.
You can’t count the same cost both ways. If you charge your bookkeeper’s time to this grant as a direct cost, it can’t also be part of your indirect rate.
Which rate you use
| Your situation | Rate you use |
|---|---|
| You have a negotiated rate with a federal agency | Your negotiated rate |
| No negotiated rate, and the federal grant rules apply | Any rate up to 15% of modified total direct costs |
| NIH award, nonprofit or similar applicant with no negotiated rate | 10% of modified total direct costs, on the older base |
| NIH SBIR or STTR, small business with no negotiated rate | Up to 40% of total direct costs |
| The notice sets its own limit or allows no indirect costs | What the notice says |
The 15% flat rate
The federal grant rules let any recipient without a current negotiated rate charge up to 15% of modified total direct costs (2 CFR 200.414(f)). You pick the rate, up to 15%. You don’t have to back it up with records, and you can keep using it for as long as you like. Once you choose it, though, you use it on all your federal awards until you negotiate a rate.
The same rule says an agency, or a pass-through entity such as a state passing federal money to you, can’t make you take a lower rate. The exception is when a law or regulation sets a lower one. The funding notice will tell you.
Does this apply to a business?
The federal grant rules mainly cover states, local governments, tribes, schools and nonprofits. An agency decides whether they apply to a business. Follow what the notice says.
What the rate is charged on
You don’t charge the flat rate on your whole budget. You charge it on your modified total direct costs. Under the current federal grant rules, that base includes:
- Salaries, wages and fringe benefits.
- Materials and supplies.
- Services and travel.
- Up to the first $50,000 of each subaward.
It leaves out equipment, building costs, rent, patient care, tuition, scholarships and fellowships, and participant support costs. It also leaves out any part of a subaward above $50,000.
Why NIH is different
In April 2026, NIH said its 2026 funding law keeps the older indirect cost rules of the Department of Health and Human Services (HHS) in place for NIH awards. So NIH took back two changes:
- The 15% flat rate. NIH uses the older 10% flat rate. Under the old rule, only an organization that has never had a negotiated rate can use it.
- The new base. NIH counts only the first $25,000 of each subaward, not $50,000.
Small businesses applying for SBIR or STTR at NIH
SBIR and STTR applicants follow a separate rule in NIH’s application instructions. If you have no negotiated rate, you can propose indirect costs of up to 40% of total direct costs.
NIH won’t negotiate a rate for Phase I. For Phase II, you generally get the rate you ask for, up to 40%, without more proof. Either way, you can charge only your real indirect costs, and no more than the rate in your award.
These awards can also pay a fee on top of your costs. That is one of the cases where a grant can pay a business a profit.
Worked example: the same budget, two sets of rules
A nonprofit with no negotiated rate plans a one-year project with $112,000 in direct costs. Here is how the base and the indirect costs come out under each set of rules.
| Direct cost | Amount | In the base: current rules | In the base: NIH |
|---|---|---|---|
| Salaries and fringe benefits | $50,000 | $50,000 | $50,000 |
| Supplies | $8,000 | $8,000 | $8,000 |
| Travel | $2,000 | $2,000 | $2,000 |
| Lab equipment (one item) | $12,000 | $0 | $0 |
| Subaward to a university partner | $40,000 | $40,000 | $25,000 |
| Base | $112,000 total | $100,000 | $85,000 |
| Indirect costs | 15% = $15,000 | 10% = $8,500 |
It’s the same project with the same costs, but the indirect costs are $6,500 apart. If you reuse a budget built for another agency in an NIH application, check this line.
A second made-up example: a small business with no negotiated rate applies for an NIH SBIR Phase I award with $100,000 in total direct costs. It could propose up to $40,000 in indirect costs.
Before you submit: check these five things
- Read the notice’s section on indirect costs. It may cap the rate, rule out indirect costs, or say which rules apply.
- Check whether you have a negotiated rate. If you do, use it.
- Work out your base. Take out equipment, rent and any subaward amount above the limit: $50,000, or $25,000 at NIH.
- Pick your rate and use it everywhere. The 15% choice covers all your federal awards, not just this one.
- Explain it in your budget justification. Say which rate you used, what is in the base, and how you did the math.
A Small Business Development Center (SBDC) can look over your grant budget for free. Find one in free help for government contracting. For the full application, follow the five steps to apply for a federal grant.
Key terms
- Direct costs
- Costs you can tie to one project, such as the hours people spend on it, supplies and travel.
- Indirect costs
- Shared costs that support all your work, such as rent, utilities and accounting. People also call them overhead, or facilities and administrative costs.
- Negotiated rate
- An indirect cost rate your organization agrees on with a federal agency, based on your real costs.
- De minimis rate
- A flat rate you can use without negotiating a rate or showing your costs.
- Modified total direct costs
- The part of your direct costs the flat rate is charged on. Some costs, such as equipment, are left out.
- Subaward
- Money you pass to a partner organization to do part of the project.
Do this in FedPath
Search federal grants on FedPath. FedPath’s grant search reads Grants.gov listings. Open a listing, then read its funding notice for any limit on indirect costs.
Free. FedPath is independent. It is not affiliated with, endorsed by, or part of the U.S. government, the Small Business Administration (SBA), SAM.gov, or any federal agency.
Common questions
Can I charge less than 15%?
Yes. You choose any rate up to 15%. Some small organizations pick less to keep more of the award for the project itself.
Can I use the 15% rate on a federal contract?
No. The rule says the flat rate can’t be used on cost-reimbursement contracts under the Federal Acquisition Regulation (FAR). Contracts follow the FAR’s own cost rules.
Will NIH switch to 15%?
NIH tied its choice to its 2026 funding law. Agencies are now funded by a stopgap through December 11, 2026. Check the notice and NIH’s guide notices before you apply.